Testing the Waters Forced Revised


 Earlier in the summer options for the future of the Wetaskiwin Aquatic Centre were presented with Option #3 being: Construct a New Wetaskiwin Regional Aquatics Centre. The estimated cost is $18.5M but with approximately $10.6M already designated and committed to the project, the outstanding balance is $7.2M.
 The City went on to admit that these numbers are the best estimates they can provide with the information they had available but were very emphatic that the numbers presented are on the conservative (safe) side.
 Also earlier this year, Wetaskiwin City Council approved plans to move into the detailed design phase, to see the project through to a point where tenders can be issued and a sponsorship plan developed in anticipation of a final decision. The tenders for the proposed Regional Aquatic Centre were received on Thursday, November 17, 2011 from Five (5) pre‐qualified contractors for the project.
 The tenders have since been reviewed and adjusted to reflect the credits and options that were identified by the contractors within tender documents. The adjusted bid results are listed below. Two bid prices are provided by each of the contractors; the first shows a tender with ‘Second Floor Included’ and the second without a second floor, or ‘Second Floor Excluded’.
 The City requested tender prices be provided showing the addition of a second floor which would diversify recreation activities. The revised tenders are as follows.

                                     Revised with        Revised no 2nd
                                                               2nd floor  floor
Chandos Construction    21,137,000.00      20,461,000.00
Clark Builders                20,303,000.00      19,293,000.00
Graham Construction     21,448,033.00       20,520,033.00
JenCol Construction      19,860,870.00       18,616,870.00
PCL                             19,813,000.00       19,279,000.00

More Stories:
  • Thorsby Council Approves Strategic Plan Submitted by Jason Gariepy, Village of Thorsby Following the municipal by-election on June 5th and throughout most of July, the Village of Thorsby Council has been busy working on setting goals and priorities for its 2014-17 ...
  • What is Leduc’s Community Character? Mayor’s Letter Submitted by City of Leduc Last month the city shared its new Leduc Strategic Plan 2014 – 2018 along with the goals and outcomes. One of the new and unique facets of this plan is the goal of ‘Community Character’ ...
  • Into, Out Of And Back Into Public Life - Jim Prentice The large brown campaign bus, decked out with ‘Jim Prentice’ signs, was strategically parked at the entrance of the Montgomery Glen Golf Course in Wetaskiwin on Friday, July 31st. This is one of many stops the bus will make ...
  • Key Stories From Leduc County Council Meeting Rib lovers, it’s time to don bibs for Leduc #1 Energy Discovery Centre’s Annual Rib Cook-off. “Come early, it goes quickly,” said past-president and historian Dan Claypool. The Cook-off takes place Aug. 10 from noon till ...
  • Air Quality Improving In Central Alberta, But Still An Issue In The North ALBERTA HEALTH SERVICES Air quality conditions in the Central and Edmonton Zones of Alberta Health Services (AHS) have improved to such an extent as to no longer pose a sustained increased risk of health concerns amongst ...




 
  • Leduc Radio Ad
  • Industrial Netmedia
  • Industrial Netmedia
  • Industrial Netmedia